Thursday, January 27, 2011

1/26/11-1/27/11

Back of building A/C ,concrete and topsoil removed


Sidewalk removed for new entrance


Northeast corner of parking lot with curbs removed an loaded in dumpster




Southeast corner of parking lot with curbs removed




Pad being prepped for post density test




Fill material behind roller waiting for results of proctor test


Back of building , water truck, slab prep


Posted by Don McClure from iPad.

Thursday, January 20, 2011

Wednesday, January 19, 2011

Daily Report January 18, 2011

Notice of Commencement - has to be signed by owner and civil engineer. Working on getting these signatures. Worknwill not be able to begin until this is done. So we will continue to add days from the actual Notice to Proceed until we can begin work.


- Posted using BlogPress from my iPad

Daily report for January 17, 2011

MLK Day. City offices closed and could not file Notice of Commencement.

Ordered container for church to store things in while work is being done.


- Posted using BlogPress from my iPad

Monday, January 17, 2011

Permit for Panama City Beach in hand

The permit for Panama City Beach was picked up on Friday, January 14, 2011.

Pre-Construction Meeting Friday, January 14, 2011

Pre-construction meeting held with owner and architect.  Actual start date will be Tuesday, January 18, 2011.  A change order for days will be generated to match start date verses Notice to Proceed.