Thursday, April 28, 2011



Brick on North side of building. Steeple base being installed



HVAC duct being installed


Sheetrock in mechanical room



Wednesday, April 27, 2011


Roof on building





Storage building stem walls formed




Drainage being installed



Thursday, April 14, 2011

Sprinkler Riser Installed


Roofing Material Delivered. Roofing starting Today




Duct Being Installed



Brick Started Yesterday


Building Backfilled Ready For Brick


Brick Flashing Being Installed



Brick Flashing




Building With Tarps . Will Have Shingles Soon.



Monday, March 28, 2011

Addition with metal cornice and tarps




Metal cornice


Metal cornice



Thursday, March 17, 2011


Working on cornice on front of building








Trusses installed for curtain wall



Tuesday, March 15, 2011

Tyvek being installed on addition



Tyvek on building and sips that were removed from back of chapel



Tyvek on building


Roofing materials delivered


Sip wall removed at back of chapel




Monday, March 14, 2011

Tap for fire sprinkler



Back flow for fire sprinkler


New fire hydrant


Decking and sheathing completed


Chapel wall


Beams for foyer




Beams for mezzanine



Building with tarps



Tuesday, March 8, 2011


Setting trusses with spreader bar



Trusses being set with framers with safety harnesses


Trusses installed


I joist being installed


LvLs installed



Strapping on sheer wall



Decking being installed



Interior wall between Primary and Relief Society


Entrance to Primary room



Monday, February 28, 2011



Trusses on truck


Trusses being unstrapped


Trusses being unloaded


Trusses on pavement on 2x4's


Lumber covered with plastic



Covering lumber with plastic



Windows removed on back and rafter tails cut off


Siding removed from back gable